January 19th, 2010
Current Activities (Jan. 19, 2010)
- Installation of utility conduits (power, phone, cable) along the east side of Saltzman Road, adjacent to the library and the Milltown Shopping Center (Walgreen/True Value Hardware).
- Installation of new storm pipe and structures along west side of Saltzman Road, between Dogwood Street and Westlawn Terrace.
- Installation of water valves and caps in preparation of beginning water line work.
- Continue with the relocation of Verizon facilities along the west side of Saltzman, just north of Dogwood (work being performed by Verizon’s contractor).
- Installation of new utility poles and line clearing along east side of Saltzman Road, north of St Pius X to Coleman Street (work being performed by PGE crews and their tree trimming contractor).
Upcoming Activities (2 weeks out)
- Continue with the installation of utility conduits along the east side of Saltzman, in front of the library and the Milltown Shopping Center (Walgreens/True Value Hardware).
- Complete installation of new storm pipe and structures along west side of Saltzman Road, between Dogwood Street and Westlawn Terrace.
- Adjustment of water vault structure just south of Burton, along the west side of Saltzman (work to be performed by Tualatin Valley Water District crews)
- Relocation of overhead utility lines and transfer of services along east side of Saltzman Road, north of St. Pius X to Coleman Street. Work for each utility will be performed by that utility’s crews or their contractor.
The project area has been designated a construction zone and the posted speed limit has been temporarily reduce to 25 mph between Cornell and the south approach of Bauer Woods Drive. All existing traffic restrictions remain in place, including turn restrictions and school speed zone.
Work Hours: 7:00 am – 5:00 pm Monday thru Friday
Lane Restrictions: 9:00 am – 3:30 pm Monday thru Friday
Posted in Uncategorized | No Comments »
December 11th, 2009
Current Activities
- Installation of utility conduits (power, phone, cable) along the east side of Saltzman Road, adjacent to the library and the Milltown Shopping Center (Walgreen/True Value Hardware).
- Installation of new storm pipe and structures along east side of Saltzman Road, adjacent to the library and the Milltown Shopping Center (Walgreen/True Value Hardware).
- Complete the installation of new storm pipe and structures along both sides of Saltzman Road, between 128th Terrace and Bauer Woods Drive.
- Continue with the relocation of Verizon facilities along the west side of Saltzman, just north of Dogwood (work being performed by Verizon’s contactor).
- Installation of new utility poles at selected locations (work being performed by PGE crews) and removal of old utility poles.
Upcoming Activities (2 weeks out)
- Continue with the installation of franchise utility conduits along the east side of Saltzman, in front of the library and the Milltown Shopping Center (Walgreens/True Value Hardware).
- Complete installation of new storm pipe and structures along east side of Saltzman Road, adjacent to the library and the Milltown Shopping Center (Walgreen/True Value Hardware).
- Begin installation of new storm pipe and structures along the west side of Saltzman Road, from north of Dogwood to Westlawn Terrace.
- Adjustment of water vault structure just south of Burton, along the west side of Saltzman (work to be performed by Tualatin Valley Water District crews)
- Begin clearing and grubbing activities for overhead utility relocations along east side of Saltzman Road, north of St. Pius X to Coleman Street (work to be performed by PGE crews or their contractor)
The project area has been designated a construction zone and the posted speed limit has been temporarily reduce to 25 mph between Cornell and the south approach of Bauer Woods Drive. All existing traffic restrictions remain in place, including turn restrictions and school speed zone.
Work Hours: 7:00 am – 5:00 pm Monday thru Friday
Lane Restrictions: 9:00 am – 3:30 pm Monday thru Friday
Posted in Uncategorized | No Comments »
November 19th, 2009
Current Activities
- Installation of utility conduits (power, phone, cable) on Saltzman Road in front of St Pius X.
- Installation of new storm pipe and structures along east side of Saltzman, across from the Burton intersection.
- Relocation of Verizon facilities along north side of Dogwood and on the west side of Saltzman, just north of Dogwood (work being performed by Verizon’s contractor).
- Installation of new utility poles at selected locations (work being performed by PGE crews).
- Installation of pressure relief valves along Lovejoy and Filbert streets (work being performed by Tualatin Valley Water District crews).
Upcoming Activities (2 weeks out)
- Continue with the installation of franchise utility conduits along the east side of Saltzman, in front of St Pius X working southward toward library and Milltown Shopping Center (Walgreens/True Value Hardware).
- Continue installation of storm pipe and structures along east side of Saltzman Road, between Burton and the south approach to Bauer Woods Drive.
- Adjustment of water vault structure just south of Burton, along the west side of Saltzman (work to be performed by Tualatin Valley Water District crews)
- Begin clearing and grubbing activities for overhead utility relocations along east side of Saltzman Road, north of St. Pius X to Coleman Street (work to be performed by PGE crews or their contractor)
The project area has been designated a construction zone and the posted speed limit has been temporarily reduce to 25 mph between Cornell and the south approach of Bauer Woods Drive. All existing traffic restrictions remain in place, including turn restrictions and school speed zone.
Work Hours: 7:00 am – 5:00 pm Monday thru Friday
Lane Restrictions: 9:00 am – 3:30 pm Monday thru Friday
Design Consultant Project Website
Washington County Project Page
Posted in Uncategorized | No Comments »
October 15th, 2009
Current Activities (Oct. 15, 2009)
- Installation of utility conduits (power, phone, cable) on Cornell Road, east of Saltzman Road
- Installation of new storm pipe and structures on Dogwood and along west side of Saltzman just north of Dogwood
Upcoming Activities (2 weeks out)
- Complete installation of franchise utility conduits on all legs of the Saltzman/Cornell intersection
- Begin installation of utility conduits north of Cornell Road, along east side of Saltzman Road, adjacent to the Milltown Shopping Center (Walgreens/True Value Hardware)
- Storm pipe and structure installation along west side of Saltzman Road, between Burton and the south approach to Bauer Woods Drive
The project area has been designated a construction zone and the posted speed limit has been temporarily reduce to 25 mph between Cornell and the south approach of Bauer Woods Drive. All existing traffic restrictions remain in place, including turn restrictions and school speed zone.
Work Hours: 7:00 am – 5:00 pm Monday thru Friday
Lane Restrictions: 9:00 am – 3:30 pm Monday thru Friday
Washington County Project Page
Posted in Uncategorized | No Comments »
October 29th, 2008
Washington County’s Department of Land Use and Transportation, along with its design engineer, David Evans and Associates, invites interested neighbors to attend an open house Thursday December 4, 2008 from 5:00 to 7:30 pm at St Pius X’s Community Center, 1280 NW Saltzman Rd, Cedar Mill regarding the upcoming improvements scheduled for Saltzman between Cornell and Thompson Roads. The project will improve and widen NW Saltzman Road to three lanes (two travel lanes and a center turn lane), make safety and intersection improvements, add bike lanes and sidewalks, street lights, storm water drainage improvements and some landscaping. This is the third in a series of public open houses that will be held for this project. The project team will present the final roadway design (Cornell to Bauer Woods Drive) and the construction schedule, and solicit issues and concerns from area residents and business owners on the design. Due to limited funding, the project has been divided into two phases: Phase 1 from Cornell Road to Bauer Woods Drive (south) and Phase 2 from Bauer Woods Drive to Thompson Road. The project is funded by property taxes through the County’s general fund (carrying on the Major Streets Transportation Improvement Program, or MSTIP). At this time, only the final design, right-of-way acquisition and construction for Phase 1 have been funded. As part of the county’s public involvement process, a Project Focus Group (PFG) made up of local residents and business owners was formed; they have been meeting periodically over the last year. The PFG was instrumental in identifying issues and concerns of area residents as well in assisting the design team in the alignment of the new road.
Final Design and Right of Way acquisition should be complete by spring 2009. Utility relocations will begin next spring.Road construction is scheduled for spring 2009 and will last through fall 2010.For further information please contact Matthew Costigan, Sr. Project Manager, 503-846-7800, or matthew_costigan@co.washington.or.us or access the project website www.deainc.com/saltzmanroad.
Washington County is committed to building and maintaining the best transportation system, ensuring the safety of all roadway users, and operating the county roadway system in a cost-effective and environmentally responsible manner.
Posted in Uncategorized | No Comments »
November 20th, 2007